Grosvenor Constructions v Musico [2004] NSWSC 344
In the Supreme Court of New South Wales, on a motion to stay execution of a judgment entered on an adjudication certificate under the Building and Construction Industry Security of Payment Act (NSW), Einstein J held that where the claimant's insolvency made it certain that the respondent's right to recoup the adjudicated amount would be rendered nugatory, the proper exercise of the discretion was to stay execution on terms, especially as a bank guarantee apparently already protected the claimant [31], [32], [33], [35], [36].
What the court decided
Grosvenor obtained an adjudication certificate under section 24 of the Building and Construction Industry Security of Payment Act 1999 (NSW) and filed it as a judgment for debt under section 25 [1]. The defendants' notice of motion sought a stay of execution of the judgment debt, entered for $486,324.77 [1]. Grosvenor had been placed under external administration, and the report to creditors put unsecured creditors' claims at $4,791,504 against $528,294 available to them [2].
An earlier determination of 18 July 2003 that the defendants pay $712,757 had been quashed by McDougall J in Musico v Davenport for jurisdictional error and denial of natural justice [6]. On 2 September 2003 the defendants had provided an unconditional bank guarantee to the court securing that sum [8]. A second determination on the same subject matter, made on 5 December 2003, fixed the adjudicated amount at $486,324.77 [9]. Bergin J stayed execution on 19 December 2003, and the court later extended the stay by consent [10]. The defendants denied any indebtedness and claimed damages of $550,839 plus GST [11].
Several judgments of the court treat provision for interim payments only as a fundamental feature of the Act [12]. The court's power to stay execution under Pt 44 r 5 of the Supreme Court Rules is exercisable whenever the requirements of justice so demand [14]. This was apparently the first case on staying judgments arising from the filing of an adjudication certificate where moneys paid would be irrecoverable through the claimant's insolvency [15]. His Honour generally adopted the defendants' submissions [16]. Although care is needed in applying decisions on a different legislative scheme, both the Act and the UK legislation provide for interim payments following adjudications [18]. In Herschel Engineering Ltd v Breen Property Ltd Dyson J refused a stay but said he would probably have granted one had there been real doubt about repayment [21]. In Baldwins Industrial Services PLC v Barr Limited a stay was granted on terms, with Barr offering to undertake to commence proceedings within a month [22]. His Honour approved a passage in Keating that a court is unlikely to grant a stay on "limited or flimsy evidence of impecuniosity" [25].
Einstein J reasoned by analogy with a stay pending appeal, noting that recouping an adjudicated amount requires fresh proceedings rather than a true appeal [27], [28], [29]. A successful claimant under the Act is entitled to the adjudicated amount, even though any payment is of an interim nature [28]. The Kalifair principles for a stay pending appeal include a real risk of prejudice not redressed by a successful appeal [29]. Because the policy of the Act is that successful claimants be paid, his Honour saw a sound reason for making stays less readily available for debts under the Act [31]. In cases such as the present the court might require more than a real risk of prejudice [31].
It was "quite plain" that without a stay the defendants, if successful in final proceedings, would suffer irreparable prejudice because payment could never be recouped [4]. Where it was certain that the defendants' rights would otherwise be rendered nugatory, the proper exercise of the discretion was to grant a stay [32]. That was especially so because the guarantee of $712,757 apparently fully protected Grosvenor's entitlement to the adjudicated amount [33]. Without a stay, the defendants' right to recoup the adjudicated amount in the "appeal" under section 32 of the Act would be rendered nugatory [35].
His Honour held that the stay should be ordered on terms [36]. Discussions were on foot about the security to remain and the parties' endeavours to arbitrate the dispute [37]. He stood the matter down so that the parties could try to agree the terms [38]. Absent consensus, and unless the parties agreed a way forward on the basis of curial proceedings, the court would give directions on the terms [39]. Those terms would require "that the plaintiff commence final proceedings within a limited period of time" and deal with how much security should remain [39].
Why it matters
This first instance decision shows that a respondent may obtain a stay of a judgment on an adjudication certificate where the claimant's insolvency would turn an interim payment into a final one. Einstein J found certainty of irreparable prejudice and apparently full security here, and left open whether anything less than certainty but more than a real risk would do. In Brodyn Pty Ltd v Davenport (2004) NSWCA 394 at paragraph 85 the Court of Appeal, without referring to this decision, said obiter that a judgment under section 25 could be stayed where the debtor had a greater claim on which it would shortly obtain judgment and money paid would be irrecoverable, though "the policy of the Act that progress payments be made" weighs against a stay. At paragraph 87 it added that the legislative intention of minimal delay and court involvement, and the possibility that the claimant's financial difficulties had been caused by the non-payment, could militate strongly against a stay in that case. In Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) HCA 4 at paragraph 51 the joint reasons of Kiefel CJ, Bell, Keane, Nettle and Gordon JJ observed, in explaining why review for non-jurisdictional error is excluded, that the risk of the advantaged party later being unable to meet a restitution order is assigned to the other party, but it did not consider stays of execution. A respondent which has already secured more than the adjudicated amount, as these defendants had, is best placed; readers should check the current text of the Act.
Numbers in square brackets are paragraph numbers of the judgment. This note summarises a decided case for education and is not legal advice. See how the notes are written.